Post date:
Monday, March 18, 2013 - 14:10
Description:
We will apply the latest security updates from Oracle on the ITCORE production database.
The patch deployment is mostly rolling and the database services will be available most of the intervention time, however there will be a short period of time where the whole ITCORE database needs to be down for clusterware patch. This downtime will happen around 18:45 and will be around 15min long.
Specific Service Detail:
All services hosted by ITCORE database (CLUMAN_S.cern.ch, CLUMAN_S, ITCORE_CDB, ITCORE_REMEDY, ITCORE_S, ITCORE_SLS, LEMONOPS_R, LEMONOPS_S, TAPELOG_S)
Reason for this intervention:
Quarterly security patch.
Effective from date:
Monday, March 25, 2013 - 18:00
End date:
Monday, March 25, 2013 - 19:30
Service Element Affected:
IT Database Service
Impact on service:
Service will be unavailable during the intervention
Posted by:
IT-DB
Unit responsible for resolution:
IT Department