CERN Accelerating science

Patching of ATLAS integration databases (INTR and INT8R) - rolling intervention

 
Description: 

The latest Oracle security patch will be applied in a rolling fashion on the ATLAS integration databases as follows:  

INTR :  Wednesday 9th from 14:00 to 15:00
INT8R: Wednesday 9th from 15:00 to 16:00
 

The patch deployment is rolling and the database services will be available during all the time, however some applications may experience session failures.

Specific Service Detail: 
ATLAS integration
Effective from date: 
Wednesday, May 9, 2012 - 14:00
End date: 
Wednesday, May 9, 2012 - 16:00
Service Element Affected: 
DB & Application Platform Service for Projects & Experiments
Impact on service: 
Service will be available but degraded
Posted by: 
IT-DB
Unit responsible for resolution: 
IT Department